Project ratings, PFI reset and Ontario Place oversight: what three publications report

Constrata Insights
14 hours ago
4 min read

Delivery confidence ratings in the UK Government Major Projects Portfolio

The National Infrastructure and Service Transformation Authority, known as NISTA, reports on the Government Major Projects Portfolio of the United Kingdom. The portfolio has 189 projects, with a total whole life cost of £924.2bn and monetized benefits of £603.6bn. The projects are delivered by 20 departments together with their arm's-length bodies. NISTA defines a Delivery Confidence Assessment as an assessment of the likelihood that a project delivers its objectives to time and cost. Ratings fall into three groups, Red, Amber and Green. Each group indicates the likelihood of successful delivery and the level of associated risks.

NISTA records the ratings at a snapshot taken at the end of March 2026. At that date, 29 projects were rated Green, or 15 percent of the portfolio. Red was assigned to 34 projects, or 18 percent of the portfolio. Amber applied to 109 projects, or 58 percent, while 17 projects, or 9 percent, were exempt.

NISTA support for Red rated projects and exits from the portfolio

NISTA reports that its Expert Advisory Team actively supports Red rated projects and programs. The team works to set those projects up for success and to guide them from a Red rating to an Amber or Green rating. NISTA also reports the outcomes for the 42 projects that left the portfolio during the reporting year. Of those, 26 reported delivery against their objectives, and seven were brought to early closure. Eight left because they no longer met the reporting criteria for the portfolio, and one was replaced by another portfolio project.

NISTA guidance on resetting operational PFI projects in the United Kingdom

NISTA guidance of November 2026 addresses the reset of operational PFI projects. NISTA states that a report it commissioned on the PFI sector defined a reset by three elements. These are a systematic review of assets and services, a plan for rectification, and relief from deductions so that improvements can be made. NISTA identifies the signs that call for a reset to be considered. These are governance challenges, strained relationships, material underperformance or concerns about the condition of assets. Without a structured review of the project, such issues may not always be visible. The guidance covers every operational PFI project, whatever its sector, size or stage. NISTA does not expect every project to require a reset.

Ontario Place redevelopment audit period and lease handover terms

The Legislative Assembly of Ontario Standing Committee on Public Accounts reported on the Ontario Place redevelopment audit in October 2026. The audit by the Office of the Auditor General of Ontario focused on the period from July 2018 to October 2024. The original lease set a payment of $250,000 by the Province of Ontario to the tenant every 180 days. The payment applied if the site was unready by January 1, 2025.

At the committee hearing, Infrastructure Ontario was asked whether the first penalty had already been paid by the Province. When the hearing took place, the site was not yet ready for handover to the tenant. Infrastructure Ontario informed the Committee that the Province had renegotiated the lease terms to extend the handover period. The renegotiation effectively waived the obligation of the Province to make the payments.

Infrastructure Ontario policy change and Committee requests on Ontario Place

Infrastructure Ontario reported to the Committee that its board approved a policy that requires best practices in competitive solicitations for realty development. The policy now applies to all future procurements. Infrastructure Ontario also informed the Committee that the policy prohibits contact with its staff outside the formal channels set out in each solicitation process.

For future government real estate projects, the Committee calls on Infrastructure Ontario to define project scopes clearly at the outset. Infrastructure Ontario is also to coordinate contractors so that overlap and site inefficiencies are avoided. Contractor progress is to be actively tracked and documented, and open or comparable procurement processes are to be used to secure competitive pricing. The Committee requests written responses to the Clerk of the Committee within 120 calendar days of tabling its report, unless otherwise specified. Responses are requested from Infrastructure Ontario, the Ministry of Infrastructure, and the Ministry of Tourism, Culture and Gaming.

Key points

  • NISTA defines a Delivery Confidence Assessment as an assessment of the likelihood that a project delivers its objectives to time and cost.

  • At the end of March 2026, NISTA rated 34 projects Red, 109 Amber and 29 Green in the Government Major Projects Portfolio of 189 projects.

  • A report cited in NISTA guidance defines a PFI reset as a review of assets and services, a plan for rectification and relief from deductions.

  • Infrastructure Ontario informed the Standing Committee on Public Accounts that the Ontario Place lease was renegotiated to extend the handover period.

  • The Committee requests written responses on its Ontario Place recommendations within 120 calendar days of tabling its report.

References

National Infrastructure and Service Transformation Authority. NISTA Major Projects Annual Report 2025-26. 2026-07-13. https://www.gov.uk/government/publications/nista-major-projects-annual-report-2025-26/nista-major-projects-annual-report-2025-26

National Infrastructure and Service Transformation Authority. PFI Reset: An Introduction. 2026-11-16. https://www.gov.uk/government/publications/introduction-to-pfi-reset/pfi-reset-an-introduction

Legislative Assembly of Ontario. Performance Audit: Ontario Place Redevelopment (2024 Annual Report of the Office of the Auditor General of Ontario). 2026-10. https://www.ola.org/en/legislative-business/committees/public-accounts/parliament-44/reports/2026-oct-27-performance-audit-ontario-place-redevelopment-2024-annual-report-office-auditor-general-

General information only. This article is not legal, engineering, financial, tax or other professional advice and does not create an advisory relationship. It relies on the references listed above, whose content may have changed since publication and has not been independently verified by the firm. It was prepared with automated drafting tools and automated quality controls. To request a correction or removal, please use the Contact page.