Analysis of contractual entitlement, notice records, claim assembly and rebuttal, in support of the client and its counsel.
WHAT IT IS
The service
Claims preparation and defense analyzes a party’s entitlement under the contract and assembles its claim from the project records, or assesses and responds to a claim made by the other party.
Each head of claim is linked to the clause relied on, the notices given and the contemporaneous records. Compliance with notice requirements and the causal link from event to effect are thereby demonstrated rather than asserted.
The same method applies to rebuttal, defense and counterclaim. Where a matter requires legal advice or representation in a proceeding, we support the client’s legal counsel. Under our policy, we do not later act as an independent expert or as a neutral on the same claim.
SUMMARY
PRACTICE
WHEN
At any time
ENGAGEMENT
As a separate engagement, or as part of a wider engagement
For a time-critical matter, mark your inquiry as urgent and state the deadline.
WHEN CLIENTS NEED IT
▸
A change or delay event has occurred, and the notice period under the contract is already running.
▸
A claim has been received, and the response must assess entitlement, notice compliance and the records cited.
▸
Several events have occurred during the work, and the entitlement arising from each must be assembled into one coherent claim.
▸
A defense and counterclaim must be prepared from the same records the claimant relies on.
WHAT YOU RECEIVE
Deliverables
The heads of claim, the timetable and the form of submission are agreed at the outset.
01
Entitlement review
A contractual and factual analysis of the provisions relied on for each event, with the notices and conditions each requires, for review by the client’s counsel where legal advice is needed.
02
Notice register
A record of each notice given or due, with its date, its content and its compliance with the contract.
03
Claim analysis
The events, the contract provisions identified, the time and money calculated and the supporting records, for the client and its counsel to adopt in a claim.
04
Rebuttal analysis
A point-by-point analysis of a claim received, assessing entitlement, notice compliance, causation and the records cited, for the client and its counsel to adopt in a response.
05
Counterclaim analysis
An analysis of a claim raised in answer, prepared from the same records, with its own entitlement, notices and evidence, for the client and its counsel to adopt.
HOW WE WORK
Entitlement demonstrated clause by clause from the records
A claim or defense depends on the contract provision and the record that support it, so each point is linked to both before it is submitted.
STEP 01
Establish the contract position
Identify the clauses, notice requirements and time bars that govern each event, and the order of precedence of the documents.
STEP 02
Gather the records
Collect correspondence, notices, minutes, schedules and cost records, and confirm what each one can prove.
STEP 03
Build or assess
Link each event to entitlement, cause and effect, and identify gaps in notice or evidence before the point is relied on.
STEP 04
Prepare and respond
Prepare the claim or response for the client or its counsel to issue in the form that the contract or forum requires, and prepare replies to the points raised.
Standards and frameworks applied
Applied where fit for purpose, in line with the client’s requirements and the contract.
APPLIED IN RESOLUTION
▸
AACE International Recommended Practices
▸
The Society of Construction Law Delay and Disruption Protocol
▸
Ciarb practice guidelines
APPLIED ACROSS ALL PRACTICES
▸
Standard forms of contract such as FIDIC, NEC, CCDC, AIA and ConsensusDocs, and non-standard contracts
▸
The laws, regulations, codes and procurement rules that apply to each project
▸
The IBA Rules on the Taking of Evidence in International Arbitration
▸
The rules of the institution or adjudication body named in each contract
WHEN IT IS USED
At any time
Standalone service
Resolution is not tied to a project phase. A client can engage it at any time, on its own or alongside Insight and Clarity, whether or not Constrata Consultants was previously engaged on the project.
Usual starting points: claim, counterclaim and defense.
RELATED SERVICES
Services often engaged together
RESOLUTION
View service
RELATED EXPERIENCE
Where this service applies
Projects our professionals have worked on in sectors where this service is commonly engaged.
TRANSIT AND RAIL
Urban rail line
Value band
Over $1B
COMMERCIAL AND MIXED USE
Residential towers
Value band
$25M to $500M
Notices, claims and adjudications are subject to time limits set by the contract and by applicable law. Contacting us does not give notice to anyone and does not stop a time limit, so take the steps that a deadline requires yourself. Where a matter needs legal advice or representation in a proceeding, our work supports the client’s legal counsel.