WHAT IT IS
The service
Commercial management and quantity surveying control the contract’s finances from award to final account, including the design period of a design-build contract. They establish the value of work done, the value of each change and the amount remaining to be paid.
Valuations are prepared from the contract’s pricing documents and the work in place, and changes are valued under the contract’s valuation rules. Every figure is traceable to the measurement, rates and records that support it.
The same method applies to subcontract accounts and the final account, so that the agreed sum at completion can be reconciled line by line to the contract sum.
SUMMARY
PRACTICE
Phases
Design
Procurement
Construction
Post-Construction
ENGAGEMENT
As a separate engagement, or as part of a wider engagement
Tell us about the project and the question.
WHEN CLIENTS NEED IT
▸
Monthly valuations need to be prepared or assessed from measured quantities and the contract rates.
▸
A backlog of changes is unpriced, and the value of each must be agreed before the account can be closed.
▸
A main contractor needs its subcontract accounts settled consistently with its own account with the owner.
▸
Construction is complete and the final account must be agreed and reconciled to the contract sum.
WHAT YOU RECEIVE
Deliverables
Reporting periods, formats and the level of measurement are agreed to match the contract’s payment terms.
01
Interim valuation
Measured work, design progress under a design-build contract, materials and change for the period, valued against the contract’s pricing documents with supporting calculations.
02
Change valuation
Each change priced under the contract’s valuation rules, using contract rates where they apply and rates built up from records where they do not.
03
Cost report
The anticipated final cost, committed and forecast change, and the movement since the previous report.
04
Subcontract account statement
The value, payments, change and retentions of each subcontract, reconciled to the main contract account.
05
Final account
The agreed final sum, built up from the contract sum, adjustments and agreed changes, with the supporting record.
HOW WE WORK
Every figure traced to measurement and records
The account is kept current throughout the work, and each valuation and change is carried forward, so that the final account is assembled from agreed figures and is not a new exercise.
STEP 01
Establish the contract basis
Review the contract sum, pricing documents, valuation rules and payment terms, and set up the commercial record.
STEP 02
Measure and value
Measure the work in place and any design progress each period, then value them with materials and change under the contract.
STEP 03
Agree on the value of each change
Price each change from its instruction and records, and negotiate its value with the other party’s representative.
STEP 04
Close the account
Assemble and agree on the final account and subcontract accounts, and reconcile both to the contract sum.
Standards and frameworks applied
Applied where fit for purpose, in line with the client’s requirements and the contract.
APPLIED IN INSIGHT
▸
AACE International Recommended Practices
▸
RICS professional standards
▸
CIQS guidance
APPLIED ACROSS ALL PRACTICES
▸
Standard forms of contract such as FIDIC, NEC, CCDC, AIA and ConsensusDocs, and non-standard contracts
▸
The laws, regulations, codes and procurement rules that apply to each project
▸
ISO standards
▸
SAVE International Value Methodology Standard and comparable international value management standards
PROJECT PHASES
When this service applies
Design
Procurement
Construction
Post-Construction
On a design-build contract, valuations and cost reports start in Design, with payment for design progress.
02
Design
Baselines for cost, schedule and risk as the design develops
03
Procurement
Tendering, evaluation, negotiation and award
04
Construction
Progress, cost and change controlled against the approved baselines
05
Post-Construction
Final account, closeout and lessons learned
RELATED SERVICES
Services often engaged together
RELATED EXPERIENCE
Where this service applies
Projects our professionals have worked on in sectors where this service is commonly engaged.
CIVIC AND JUSTICE
Correctional complex
Value band
$500M to $1B
COMMERCIAL AND MIXED USE
High-rise office tower
Value band
Over $1B
