WHAT IT IS
The service
Risk management identifies the risks to a project’s cost and schedule, assesses them and determines the contingency required to cover them at a stated confidence level.
The service is based on a risk management framework and a risk register agreed with the client. Quantitative risk analysis combines estimate uncertainty and risk events with the schedule logic and the cost plan.
The results inform the business case, award decisions and the drawdown of contingency during construction. Where they support a funding decision, we work with the funder’s advisors.
SUMMARY
PRACTICE
Phases
All phases
ENGAGEMENT
As a separate engagement, or as part of a wider engagement
Tell us about the project and the question.
WHEN CLIENTS NEED IT
▸
A business case or funding approval requires a contingency supported by quantitative risk analysis rather than set as a percentage.
▸
The risk register lists many risks but does not show their effect on cost or completion.
▸
A contractor is pricing a tender and needs to quantify the risk in its price and schedule.
▸
Contingency is being drawn down, and the remaining amount must be assessed against the open risks.
WHAT YOU RECEIVE
Deliverables
The framework, the confidence levels used and the format of results are agreed with the client at the outset.
01
Risk management framework
The process, roles, scoring criteria and review cycle for managing risk on the project, set out for the project team to follow.
02
Risk register
Each risk with its cause, owner, likelihood, effect on cost and schedule, response and current status.
03
Quantitative risk analysis
Probabilistic cost and schedule results showing the range of outcomes and the confidence level for each value and date.
04
Contingency recommendation
The contingency for cost and time at the chosen confidence level, with the risks that contribute most to it.
05
Risk workshop records
The attendees, risks identified, assessments agreed and actions assigned at each workshop.
HOW WE WORK
Risk measured in cost and time
Each risk is expressed as its effect on cost and time, so that contingency, responses and decisions can be compared on a common basis.
STEP 01
Agree on the framework
Set the risk process, scoring criteria and ownership with the client, aligned with the contract’s allocation of risk.
STEP 02
Identify and assess
Run workshops with the project team to identify risks, assess them and agree on their owners and responses.
STEP 03
Model and quantify
Combine estimate uncertainty and risk events with the cost plan and schedule logic to produce a range of outcomes.
STEP 04
Set and monitor contingency
Recommend contingency at the agreed confidence level and review it as risks close or new ones arise.
Standards and frameworks applied
Applied where fit for purpose, in line with the client’s requirements and the contract.
APPLIED IN CLARITY
▸
AACE International Recommended Practices
▸
PMI standards for project, program, portfolio and risk management
▸
CMAA Construction Management Standards of Practice
APPLIED ACROSS ALL PRACTICES
▸
Standard forms of contract such as FIDIC, NEC, CCDC, AIA and ConsensusDocs, and non-standard contracts
▸
The laws, regulations, codes and procurement rules that apply to each project
▸
ISO standards
▸
Recognized earned value management guidelines
PROJECT PHASES
When this service applies
All phases
01
Pre-Design
Business case, budget and delivery strategy
02
Design
Baselines for cost, schedule and risk as the design develops
03
Procurement
Tendering, evaluation, negotiation and award
04
Construction
Progress, cost and change controlled against the approved baselines
05
Post-Construction
Final account, closeout and lessons learned
RELATED SERVICES
Services often engaged together
RELATED EXPERIENCE
Where this service applies
Projects our professionals have worked on in sectors where this service is commonly engaged.
POWER AND UTILITIES
Power station refurbishment
Value band
Over $1B
WATER AND WASTEWATER
Water transmission pipeline
Value band
Over $1B