WHAT IT IS
The service
As independent certifier, we determine whether the conditions for milestones, completion and payment have been met under public-private partnership (P3) and similar contracts. We act for neither the owner nor the project company and its lenders.
Each certificate applies the criteria set by the contract and is based on the evidence the contract requires, which we review for completeness and consistency. Where evidence is missing or a criterion is not met, we state this in writing and identify what remains outstanding.
Under our policy, we do not accept an appointment as independent certifier on a project where we advise, or have advised, a party on that project, and we disclose any other relationship with the parties before we accept.
SUMMARY
PRACTICE
Phases
Construction
Post-Construction
ENGAGEMENT
As a separate engagement, or as part of a wider engagement
Tell us about the project and the question.
WHEN CLIENTS NEED IT
▸
A project agreement requires an independent certifier to confirm milestone achievement before a payment is released.
▸
Substantial or final completion must be certified against criteria that the owner, the project company and lenders all rely on.
▸
The project company and the owner disagree on whether the evidence submitted meets the completion criteria.
▸
Lenders require drawdowns to be linked to progress certified under the terms of the contract.
WHAT YOU RECEIVE
Deliverables
The certificates, evidence requirements and reporting are set by the contract and confirmed with all parties at appointment.
01
Certification protocol
The criteria, evidence requirements, submission procedure and timetable for each certificate, drawn from the contract and agreed with the parties.
02
Evidence review
A record of the evidence submitted for each certificate, its compliance with the contract and any gaps identified.
03
Milestone certificate
A certificate confirming that a payment milestone has been achieved under the contract’s criteria, or a statement of the reasons it has not.
04
Completion certificate
Certification of completion at each stage the contract defines, with any outstanding items listed against the criteria.
05
Certifier’s report
A periodic report to all parties on submissions received, certificates issued or withheld, and matters approaching certification.
HOW WE WORK
Certification on the contract’s criteria and evidence
As independent certifier, we apply the contract as agreed by the parties, communicate with all parties equally and rely on the documentary evidence the contract specifies.
STEP 01
Agree on the protocol
Set out with the parties the criteria, evidence and procedure for each certificate the contract requires.
STEP 02
Receive the submission
Log each submission and check that the evidence the contract requires has been provided in full.
STEP 03
Review the evidence
Assess the evidence against the contract criteria and seek clarification from the submitting party where needed.
STEP 04
Certify or withhold
Issue the certificate, or state in writing which criteria remain unmet and what evidence is still required.
Standards and frameworks applied
Applied where fit for purpose, in line with the client’s requirements and the contract.
APPLIED IN INSIGHT
▸
AACE International Recommended Practices
▸
RICS professional standards
▸
CIQS guidance
APPLIED ACROSS ALL PRACTICES
▸
Standard forms of contract such as FIDIC, NEC, CCDC, AIA and ConsensusDocs, and non-standard contracts
▸
The laws, regulations, codes and procurement rules that apply to each project
▸
ISO standards
▸
SAVE International Value Methodology Standard and comparable international value management standards
PROJECT PHASES
When this service applies
Construction
Post-Construction
04
Construction
Progress, cost and change controlled against the approved baselines
05
Post-Construction
Final account, closeout and lessons learned
RELATED SERVICES
Services often engaged together
RELATED EXPERIENCE
Where this service applies
Projects our professionals have worked on in sectors where this service is commonly engaged.
ROADS, BRIDGES AND TUNNELS
Motorway public-private partnership
Value band
Over $1B
HEALTHCARE
Hospital replacement
Value band
$25M to $500M