Forensic delay and disruption analysis
RESOLUTION · DISPUTE RESOLUTION
Forensic delay and disruption analysis
Delay analysis methods chosen to fit the project records.
WHAT IT IS
The service
Forensic delay and disruption analysis establishes what delayed or disrupted the work, by how much, and which party bears the risk of each event under the contract.
The method is selected to suit the records that the project holds, from the baseline schedule and schedule updates to progress records and correspondence. Every conclusion is traced to those records.
Delay is analyzed once a claim or a dispute exists: after award, in Design under a design-build contract or in Construction, or when we are engaged to prepare a claim or counterclaim. The analysis then supports negotiation, settlement and formal proceedings.
WHEN CLIENTS NEED IT
▸
An extension of time has been claimed or refused, and the critical path is disputed.
SUMMARY
PRACTICE
Phases
Design
Construction
Post-Construction
ENGAGEMENT
As a separate engagement, or as part of a wider engagement
For a time-critical matter, mark your inquiry as urgent and state the deadline.
▸
Concurrent delay is alleged, and responsibility for each period of delay must be separated.
▸
Disruption to the work is claimed alongside, or instead of, delay to completion.
▸
Counsel, an adjudicator or a tribunal needs the delay events analyzed from the contemporaneous records.
WHAT YOU RECEIVE
Deliverables
Scope and format are agreed at the outset and follow the requirements of the contract and the forum.
01
Records review
An assessment of the schedules, progress records and correspondence available, and of what they can support.
02
Method statement
The analysis method selected, with the reasons it fits the records, the contract and the forum.
03
Delay analysis
The critical path through each period, the delay events, their effect on completion and any concurrency.
04
Disruption analysis
The loss of productivity caused by each event, measured against comparable unaffected work where the records allow.
05
Report and supporting files
A written report with the supporting schedules and an audit trail to the records, suitable for negotiation, adjudication or formal proceedings.
HOW WE WORK
A method chosen to fit the project records
No single method or standard is applied by default. The method is selected according to the records available, the contract and the forum in which the analysis will be used.
STEP 01
Review the records
Collect the schedules, schedule updates, daily records and correspondence, and assess them for completeness and reliability.
STEP 02
Select the method
Choose the analysis method that the records, the contract and the forum can support, and state why.
STEP 03
Analyze and verify
Establish the critical path, the effect of each event and any concurrency, and verify the result against the facts.
STEP 04
Report
Set out the findings, the method and the evidence in a form the parties, counsel or tribunal can rely on.
Standards and frameworks applied
Applied where fit for purpose, in line with the client’s requirements and the contract.
APPLIED IN RESOLUTION
▸
AACE International Recommended Practices
▸
The Society of Construction Law Delay and Disruption Protocol
▸
Ciarb practice guidelines
APPLIED ACROSS ALL PRACTICES
▸
Standard forms of contract such as FIDIC, NEC, CCDC, AIA and ConsensusDocs, and non-standard contracts
▸
The laws, regulations, codes and procurement rules that apply to each project
▸
The IBA Rules on the Taking of Evidence in International Arbitration
▸
The rules of the institution or adjudication body named in each contract
PROJECT PHASES
When this service applies
Design
Construction
Post-Construction
Delay is analyzed once a claim or a dispute exists: after award, in Design under a design-build contract or in Construction, or when we are engaged to prepare a claim or counterclaim.
02
Design
Baselines for cost, schedule and risk as the design develops
04
Construction
Progress, cost and change controlled against the approved baselines
05
Post-Construction
Final account, closeout and lessons learned
RELATED SERVICES
Services often engaged together
RESOLUTION
View service
RELATED EXPERIENCE
Where this service applies
Projects our professionals have worked on in sectors where this service is commonly engaged.
ROADS, BRIDGES AND TUNNELS
Highway and interchange
Value band
$25M to $500M
POWER AND UTILITIES
Gas turbine power plant
Value band
$500M to $1B
Notices, claims and adjudications are subject to time limits set by the contract and by applicable law. Contacting us does not give notice to anyone and does not stop a time limit, so take the steps that a deadline requires yourself. Where a matter needs legal advice or representation in a proceeding, our work supports the client’s legal counsel.
An expert’s duty is to the court or tribunal, not to the party that gives the instructions. Before we accept instructions, we check for conflicts and disclose any relationship that could reasonably be seen to affect independence. Each expert must disclose any such relationship or interest to us. Under our policy, we do not give expert evidence on a matter where we have provided consulting support to a party or acted as contract administrator on the project. No fee for expert evidence depends on the outcome.