Construction delay and disruption analysis: what three publications report
AACE International guidance on system dynamics for disruption claims
An AACE International item dated October 2025 describes a recommended practice on system dynamics modeling for disruption. The practice gives guidance on using the method to produce expert evidence of entitlement to compensation. It addresses claims that arise from disruption on construction and engineering projects. AACE International states that system dynamics helps identify and quantify the root causes, damages and delays of project disruption. The practice is framed around a contract between an owner and its prime contractor. Its scope extends to every party contracted to perform work on the project, including subcontractors and suppliers.
The AACE International practice sets out a suggested process based on the system dynamics modeling approach. The process aims to identify the root causes of project disruption and the resulting damages, delays and responsibilities. AACE International states that the process applies to every common contracting strategy and delivery method in engineering and construction. The practice describes the method as particularly useful for identifying and quantifying the cumulative impact of disruption.
Causes of delay reported in the SME State of Trade Survey for 2026
The SME State of Trade Survey of the Federation of Master Builders and the Chartered Institute of Building covers activity from January to June 2026. It looks ahead to July to December 2026. The survey was issued between 3 September and 21 September 2026 and received 416 completed responses. In the first half of 2026, 8 percent of respondents reported no delays to their projects or jobs.
The Federation of Master Builders and the Chartered Institute of Building rank the causes cited by respondents that faced delays. Delays in the planning process were the most common cause, at 31 percent. Market uncertainty followed at 27 percent, and extreme weather events at 20 percent. Other contributing factors were delays to materials or equipment at 19 percent, changing project parameters at 18 percent and changing regulations at 15 percent.
Skills shortages and weather disruption reported by SME construction firms
The SME State of Trade Survey reports the effects of skills shortages on small and medium-sized construction businesses. Almost half of respondents, 47 percent, reported that shortages had caused job delays. Around one in five, 21 percent, reported that shortages had led to canceled jobs. A further 29 percent reported that skills shortages had limited their plans to recruit new staff. Workforce shortages had prevented business growth or expansion for 18 percent of respondents.
The SME State of Trade Survey also records the impacts reported by businesses that experienced weather-related disruption. Reduced worker welfare was the most common impact, at 76 percent, followed by reduced productivity at 74 percent. Health and safety restrictions limited work activity for 60 percent of those businesses. The inability to complete outdoor work was reported at 54 percent for heatwaves and at 57 percent for rainfall.
HS2 schedule position reported to the UK Parliament in May 2026
The Department for Transport of the United Kingdom reported to Parliament on HS2 in May 2026. The statement draws on reset work carried out on the program. That work places progress on completing the civil engineering for the whole route at least four years behind the original schedule. The reset also found that the time to test and commission HS2 for a reliable and safe service had been underestimated by another three years.
The Department for Transport states that the opening stage of HS2 is now expected to open between May 2036 and October 2039. That stage will run the first trains from Old Oak Common, in west London, to Birmingham Curzon Street. The full scheme extends from Euston in the south to Handsacre Junction in the north. The department estimates that the full scheme will open between May 2040 and December 2043.
New HS2 baseline for scope, delivery and performance monitoring
The Department for Transport reports that HS2 Ltd will develop a new baseline for the program in the year after the May 2026 statement. The baseline is to set out a clear scope of work and a path to delivery. It is also to serve as the basis of performance monitoring and reporting by the department. That monitoring is intended to keep the project robustly managed once the reset is complete.
Key points
AACE International describes system dynamics modeling as a method for producing expert evidence of entitlement to compensation for disruption claims.
The AACE International process identifies root causes, damages, delays and responsibilities, and applies to every common contracting strategy and delivery method.
In the SME State of Trade Survey, planning delays were the most common cause of delay at 31 percent. Market uncertainty followed at 27 percent.
The Department for Transport estimates that the full HS2 scheme will open between May 2040 and December 2043.
References
AACE International. New RP 135R-24: System Dynamics Modeling to Demonstrate Entitlement to Project Disruption Costs. 2025-10-20. https://source.aacei.org/2025/10/20/new-recommended-practice-135r-24-system-dynamics-modeling-to-demonstrate-entitlement-to-project-disruption-costs/
Federation of Master Builders and Chartered Institute of Building. The SME State of Trade Survey: The first half of 2026. 2026-11. https://www.ciob.org/media/3995/download
Department for Transport. HS2 6-monthly report to Parliament: May 2026. 2026-05-19. https://www.gov.uk/government/speeches/hs2-6-monthly-report-to-parliament-may-2026
General information only. This article is not legal, engineering, financial, tax or other professional advice and does not create an advisory relationship. It relies on the references listed above, whose content may have changed since publication and has not been independently verified by the firm. It was prepared with automated drafting tools and automated quality controls. To request a correction or removal, please use the Contact page.