Payment notices and dispute time limits in 2026: what three publications report
Proper invoices and payment periods under the Canadian federal prompt payment statute
This article reports what the Department of Justice of Canada and the Department for Business and Trade publish on payment notices and dispute time limits. It covers the Canadian federal prompt payment statute, its dispute resolution regulations and proposals for construction payment in the United Kingdom.
The Federal Prompt Payment for Construction Work Act of Canada, published by the Department of Justice of Canada, sets payment periods for federal construction work. Her Majesty or the service provider pays the contractor for all of the construction work that the proper invoice covers. Payment is due no later than the 28th day after the proper invoice is received. Under the Act, no requirement for prior verification of the construction work applies to a proper invoice.
Notices of non-payment and payment down the subcontracting chain
Her Majesty or the service provider may decline payment for some or all of the invoiced construction work. Declining payment requires a notice of non-payment from Her Majesty or the service provider to the contractor. The notice is given no later than the 21st day after the proper invoice is received.
A contractor paid by Her Majesty or a service provider pays each of its subcontractors for the work they invoiced. That work is the construction work covered by the proper invoice and paid for. The payment is due no later than the 35th day after Her Majesty or the service provider received the proper invoice. The contractor may decline to pay a subcontractor for some or all of the work. It does so by giving the subcontractor a notice of non-payment no later than the 28th day after the proper invoice is received.
Adjudication of non-payment disputes under the Canadian federal statute and regulations
Under the Act, a contractor or subcontractor may seek adjudication where it has not been fully paid within the time limit for payment. The relevant time limit is the one the Act provides or, when applicable, a shorter limit in its contract. The dispute concerns non-payment by the party that owes payment under the contract.
The Federal Prompt Payment for Construction Work Regulations (Dispute Resolution) set the period for the determination. The adjudicator makes the determination no later than 20 days after receiving the response under section 18. Where there is no response, the 20 days run from the day the response was due. The adjudicator may extend that time limit by up to five days. A longer extension requires consent from all parties and from the adjudicator.
The determination of the adjudicator binds the parties to the dispute unless they reach a written agreement. A court order or arbitral award may also set the determination aside. A party ordered by the adjudicator to pay makes that payment by the 10th day after it receives the determination. A different time limit applies where the determination sets one out.
Proposed time limit for raising supplier disputes in the United Kingdom
The Department for Business and Trade published its response to the Late Payment Consultation in March 2026. The response states an intention to introduce a time limit for raising disputes. The consultation included a deadline of 30 days for raising a dispute with a supplier over a good or service. Under that proposal, a business raising a dispute after 30 days would pay invoices in full within agreed payment terms. Late payments would accrue statutory interest.
The Department for Business and Trade response states that any new dispute policy is intended not to cut across existing ones. For construction contracts, the response states that a separate measure will be taken forward. That measure is aligned with the existing payment notice mechanisms.
Proposed prohibition of retention payments in United Kingdom construction contracts
The Department for Business and Trade response proposes legislation to prohibit deducting and withholding retention payments under the terms of construction contracts. Given the ambition of that policy, the Government will hold further consultation with interested parties on the impact of the measure. That consultation comes before a final decision on implementation.
Key points
Under the Canadian Federal Prompt Payment for Construction Work Act, the contractor is paid by the 28th day after a proper invoice is received.
A notice of non-payment to the contractor is given no later than the 21st day after the proper invoice is received.
The dispute resolution regulations set 20 days from receipt of the response for the determination, which the adjudicator may extend by up to five days.
The Department for Business and Trade response of March 2026 states an intention to introduce a time limit for raising disputes.
The same response proposes legislation to prohibit deducting and withholding retention payments under construction contracts.
References
Department of Justice Canada. Federal Prompt Payment for Construction Work Act (S.C. 2019, c. 29, s. 387). 2026-10-29. https://laws-lois.justice.gc.ca/eng/acts/F-7.7/FullText.html
Department of Justice Canada. Federal Prompt Payment for Construction Work Regulations (Dispute Resolution) (SOR/2023-271). 2026-10-29. https://laws-lois.justice.gc.ca/eng/regulations/SOR-2023-271/FullText.html
Department for Business and Trade. Time to pay up: Government response to 2025 Late Payment Consultation. 2026-03. https://assets.publishing.service.gov.uk/media/69c2c7c413f1436476e443a2/late-payments-consultation-response.pdf
General information only. This article is not legal, engineering, financial, tax or other professional advice and does not create an advisory relationship. It relies on the references listed above, whose content may have changed since publication and has not been independently verified by the firm. It was prepared with automated drafting tools and automated quality controls. To request a correction or removal, please use the Contact page.