Expert witness evidence and multi-prime delay analysis: what four publications report
Ciarb report and survey on party-appointed expert witnesses in arbitration
The Chartered Institute of Arbitrators released its report on party-appointed expert witnesses in international arbitration in July 2026, under the subtitle Effectiveness and Best Practice. A two-year project preceded the report, shaped by practitioner feedback and by themes from the 2025 Roebuck Lecture. The institute presents the report as an advisory reference tool on the use, communication and understanding of expert witness evidence in international arbitration proceedings.
The evidence base of the Ciarb report combines a global survey with consultation across disciplines and across common and civil law traditions. The survey received 419 responses. Its respondents worldwide comprised arbitrators, expert witnesses, and both external and in-house counsel, across a broad range of roles in the arbitral process.
The report ties the effectiveness of expert evidence to a more proactive and structured role for tribunals. The role has four parts. They are early focus on the issues, engagement with methodology and data, reading of reports as served, and clear procedural direction. The recommendations stay adaptable to the needs of each case. Survey respondents agreed with encouraging tribunals to read expert witness reports as they are served. Agreement came from 67 percent of arbitrators and 89 percent of expert witnesses. It also came from 92 percent of external counsel and 83 percent of in-house counsel.
Survey results on early instruction and early meetings of expert witnesses
In the Ciarb survey, 71 percent of all respondents favored the appointment of expert witnesses during the pre-arbitration stage. The report records this as a clear overall preference for early instruction. Respondents also supported tribunals requiring early expert witness meetings. Such meetings agree common data sets and methodologies or explain the approach of each expert. Agreement stood at 81 percent among arbitrators, 81 percent among expert witnesses, 90 percent among external counsel and 83 percent among in-house counsel.
Over-instruction of expert witnesses by counsel in the Ciarb survey
The Ciarb report defines over-instruction as instructions to an expert witness that improperly shape, constrain or direct the opinions of that expert. The defining feature is that the instructions compromise, or appear to compromise, the independence and objectivity of the expert witness. In-house counsel reported a unanimous view that counsel over-instruct expert witnesses often or very often. External counsel reported the same view at 60 percent. Among expert witnesses, 73 percent reported over-instruction as occurring never or not often. The report describes this divergence as one of the starkest splits by role in its entire data set.
Joint expert reports, joint statements and the involvement of counsel
On sequence, 78 percent of expert witnesses in the Ciarb survey favored issuing the joint expert witness report after the individual expert witness reports. The corresponding shares were 65 percent of arbitrators, 58 percent of external counsel and 69 percent of in-house counsel. The Society of Construction Law published a paper in September 2026 that takes the perspective of an expert on the joint statement. The paper asks whether guidance under recent case law needs a rethink. Under that guidance, construction lawyers keep away from the process of drafting the joint statement.
AACE International practice on forensic schedule analysis across several prime contracts
AACE International announces a new recommended practice on forensic schedule analysis on a multi-prime project. Multi-prime contracts, the practice states, introduce additional considerations. Determining the causes of delay under them may call for deeper analysis than the same task requires under a single prime contract. Pacing and concurrency may weigh more as factors than under single prime contract delivery. Individual contractors can be delayed without any impact on overall project completion.
AACE International also states that delays caused by one specific prime contractor can affect the work of other prime contractors. That effect arises whether or not the affected work of those primes lies on the critical path of the overall project.
Key points
The Chartered Institute of Arbitrators survey on party-appointed expert witnesses received 419 responses from arbitrators, expert witnesses and counsel.
In the Ciarb survey, 81 percent of arbitrators supported tribunals requiring early expert witness meetings on common data sets and methodologies.
In the Ciarb survey, 71 percent of all respondents favored appointing expert witnesses during the pre-arbitration stage.
AACE International states that one prime contractor can delay other prime contractors whether or not their work is on the critical path.
References
Chartered Institute of Arbitrators. Ciarb publishes report on the effectiveness of expert witness evidence in arbitration. 2026-07-09. https://www.ciarb.org/news-listing/ciarb-publishes-report-on-the-effectiveness-of-expert-witness-evidence-in-arbitration/
Chartered Institute of Arbitrators. Report on Party-Appointed Expert Witnesses in International Arbitration: Effectiveness and Best Practice. 2026-07. https://www.ciarb.org/media/yzllsqrs/ew-report.pdf
Society of Construction Law. Did you Really Mean to Say That? Of Lawyers and the Experts’ Joint Statement. 2026-09. https://www.scl.org.uk/papers/did-you-really-mean-say-lawyers-and-experts-joint-statement
AACE International. New Recommended Practice 141R-25: Forensic Schedule Analysis on a Multi-Prime Project. 2026-10-16. https://communities.aacei.org/blogs/aace-source/2026/10/16/new-rp-141r-25-forensic-schedule-analysis
General information only. This article is not legal, engineering, financial, tax or other professional advice and does not create an advisory relationship. It relies on the references listed above, whose content may have changed since publication and has not been independently verified by the firm. It was prepared with automated drafting tools and automated quality controls. To request a correction or removal, please use the Contact page.