Independent certification and PFI payment assurance in 2026: what three publications report
Role, fees and agreements of the Independent Certifier in an Ontario project agreement
In the 2021 Infrastructure Ontario project agreement for the Advance Tunnel for the Scarborough Subway Extension, Schedule 6 is the Independent Certifier Agreement. That schedule sets out the role, obligations and functions of the Independent Certifier in general terms. Project Co and the Contracting Authority share equally the responsibility for paying all fees and costs of the certifier. Neither party may sign any other agreement with the certifier on the project without written consent from the other party. Project Co is also to ensure that no Project Co Party enters into a separate agreement with the certifier.
Infrastructure Ontario restrictions on independent certifier roles in P3 projects
The Procurement Policy of Infrastructure Ontario, dated September 2026, sets restrictions for its public private partnership projects, known as P3 projects. The restrictions apply where execution of the Project Agreement requires contemporaneous execution of multi-party ancillary agreements. In those projects, the party acting as independent certifier is not to be retained as technical advisor to the lenders. It is also not to advise either party to the Project Agreement, or their related entities, on that agreement. The restriction covers acting as transaction advisor to either party.
Substantial completion review periods and the Minor Deficiencies List
The Scarborough tunnel project agreement sets a review period for the Substantial Completion Notice. The Independent Certifier has two Business Days from receipt of the notice from Project Co to complete its review. The review determines whether the notice includes all of the Substantial Completion Deliverables. Those deliverables are the items described in the Substantial Completion Deliverables List.
In connection with the Substantial Completion Notice, the Independent Certifier prepares the Minor Deficiencies List. The agreement requires the list as soon as reasonably practicable. In any event, the list is due before the Substantial Completion Certificate is issued. The Independent Certifier is not to withhold the Substantial Completion Certificate solely because Minor Deficiencies exist.
Private Finance Initiative contracts and the unitary charge in the United Kingdom
The National Infrastructure and Service Transformation Authority defines the Private Finance Initiative, or PFI, as a type of public private partnership. The initiative was developed in the United Kingdom. PFI has served to design, build, refurbish, maintain and operate assets. The authority lists hospitals, schools and housing among those assets, together with street lighting and waste disposal facilities. The unitary charge is the single annual amount that the project agreement specifies to cover all project costs over its life. The charge is usually stated as an annual figure and paid in monthly installments.
The authority describes the payment mechanism as the link between performance and money. Deductions follow availability failures and breaches of service and performance criteria. They are designed to give the PFI Co an incentive to perform and to compensate the contracting authority in part. That compensation applies where assets are not available or where services fall short of the service standards. A partly unavailable asset leads to deductions from the unitary charge. If the whole asset is unavailable and the PFI Co delivers no service, the mechanism typically makes no unitary charge payable for that period.
Performance self-monitoring, KPIs and verification in PFI contract management
Under PFI contracts, the PFI Co monitors its own performance and reports it against the performance and service criteria. The National Infrastructure and Service Transformation Authority states that this reporting is to be transparent and accurate. The reported performance is not to be accepted without verification. Key performance indicators, or KPIs, apply to the service and performance criteria. They are measured through failure points and the resulting deductions. Even with every KPI failure point triggered, deductions are usually a small share of the total unitary charge.
The guidance of the authority calls for review of monthly performance reports for completeness. The review also covers consistency of those reports with the contractual requirements. The guidance further calls for sampling of underlying records, such as helpdesk logs and failure reports. The sample confirms that issues are logged and categorized correctly.
Key points
Infrastructure Ontario bars the independent certifier on P3 projects from acting as technical advisor to the lenders or advising either party to the Project Agreement.
In the Scarborough tunnel project agreement, Project Co and the Contracting Authority share equally all fees and costs of the Independent Certifier.
The Independent Certifier has two Business Days to review whether a Substantial Completion Notice includes all listed Substantial Completion Deliverables.
The National Infrastructure and Service Transformation Authority defines the unitary charge as the single annual amount in a PFI project agreement, paid in monthly installments.
PFI Co performance reports are not to be accepted without verification, and deductions reduce the unitary charge when part of the asset is unavailable.
References
Infrastructure Ontario. Ontario Infrastructure and Lands Corporation Procurement Policy. 2026-09-24. https://www.infrastructureontario.ca/4aabfb/contentassets/4b13cce97461496482259638d7eb1cd2/io-procurement-policy-sept-2026.pdf
Infrastructure Ontario. Project Agreement, Redacted Version, to Design, Build and Finance the Advance Tunnel for the Scarborough Subway Extension. 2021. https://www.infrastructureontario.ca/contentassets/42ee9de7c0bb413b9f4ec25110a37c27/atsse20redacted20pa.pdf
National Infrastructure and Service Transformation Authority. NISTA Contract Management Guidance: PFI Foundations. 2026-03-26. https://www.gov.uk/government/publications/pfi-foundations-for-contract-managers/nista-contract-management-guidance-pfi-foundations
General information only. This article is not legal, engineering, financial, tax or other professional advice and does not create an advisory relationship. It relies on the references listed above, whose content may have changed since publication and has not been independently verified by the firm. It was prepared with automated drafting tools and automated quality controls. To request a correction or removal, please use the Contact page.