Earned value management in 2026: what two publications report
Scope of the ISO standard on earned value management
The International Organization for Standardization, known as ISO, published its standard on earned value management in 2026. The standard gives guidance on earned value management practices in project, program and portfolio management. It applies to organizations of any type, public or private, and of any size or sector. It also applies to any project, program or portfolio, whatever its complexity, size or duration. Guidance on particular processes, methods or tools for earned value management falls outside the standard.
Contents of the ISO earned value standard and its integrated baseline review annex
The ISO standard on earned value management sets out five areas of content. The first describes why earned value management is used and what benefits it brings. The second covers its integration and relationship with project, program and portfolio management. The third gives an overview of the processes, together with a description of each process. The fourth sets out the basic needs for an earned value management system. The fifth covers the use of such a system.
Annex A of the ISO earned value standard describes an integrated baseline review. The standard places this review in an annex instead of the main text. Government organizations and their contractors use the integrated baseline review. Most organizations, the standard states, do not use it most of the time, and the annex position reflects that pattern of use.
Planned value, earned value and actual cost as defined by PMI
The Project Management Institute, PMI, defines planned value, or PV, as the budgeted cost of the work scheduled for completion by the time of measurement. This value is the baseline, expressed as the intended cost of the planned work. Earned value, or EV, measures the work performed at its budgeted value. It counts finished work at its originally planned cost, and it excludes hours logged and dollars spent.
Actual cost, or AC, is the amount spent to perform the work. PMI equates the three measures with the older terms BCWS, BCWP and ACWP. PMI states that the method needs a foundation of a clear scope statement and a work breakdown structure, or WBS, oriented to deliverables. From the same three numbers, PMI derives two variances and two indices. These are schedule variance, cost variance, the schedule performance index, or SPI, and the cost performance index, or CPI.
A worked earned value example with schedule and cost indices
PMI sets out a worked example on a project with a budget of 100,000 dollars, measured four months after the start. By that point, the planned value of work is 40,000 dollars. The work actually finished is worth 36,000 dollars, which is its earned value. The actual cost of that finished work is 45,000 dollars.
In the PMI example, the cost performance index is 0.80 and the schedule performance index is 0.90. PMI describes this combination as a particular kind of warning. The project is slightly behind schedule and meaningfully over budget. According to PMI, that pattern usually indicates that resources are being consumed faster than results are produced, beyond a simple delay to the schedule.
Estimate at completion and the to-complete performance index
PMI defines the estimate at completion, or EAC, as the forecast of the final cost of a project. It projects the cost of the whole job on the condition that current performance continues. In the worked example, the forecast is a finish at 125,000 dollars on the budget of 100,000 dollars. The overrun of 25,000 dollars becomes visible in month four, instead of in month ten.
The to-complete performance index, or TCPI, is a companion metric in the PMI guide. It gives the cost efficiency required on the remaining work for the project to still finish on budget. PMI states that a TCPI well over the current CPI points to a target that probably cannot be met without a real change of plan.
Key points
The ISO standard on earned value management gives guidance for organizations of any type, size or sector and for any project, program or portfolio.
Annex A of the ISO earned value standard describes an integrated baseline review, which government organizations and their contractors use.
PMI defines earned value as the budgeted value of the work performed and planned value as the budgeted cost of the work scheduled.
In the PMI worked example, a project with a budget of 100,000 dollars is forecast to finish at 125,000 dollars, an overrun of 25,000 dollars.
References
ISO (International Organization for Standardization). ISO 21508:2026 Project, programme and portfolio management: Earned value management. 2026-02. https://www.iso.org/standard/87899.html
Project Management Institute (PMI). Earned Value Management: A Guide to Reading the Numbers. 2026-08-31. https://www.pmi.org/blog/earned-value-management
General information only. This article is not legal, engineering, financial, tax or other professional advice and does not create an advisory relationship. It relies on the references listed above, whose content may have changed since publication and has not been independently verified by the firm. It was prepared with automated drafting tools and automated quality controls. To request a correction or removal, please use the Contact page.